SJVN has signed a letter of intent for the construction of a 2.4 GW pumped storage project of the Indian state government of Mizoram. The pumped storage project has been proposed across Darzo Nallah, a tributary of the Tuipui River.
This is SJVN’s first project in the state of Mizoram. It is an on-stream closed loop type and comprises eight units of 300 MW each.
“The annual energy generation with 95% installation availability will be 4,993.20 MU. The annual input energy required to pump water to the upper reservoir is estimated at 6,331.66 MU with a plant availability of 95%,” SJVN said.
The project is expected to be completed in 72 months. The final agreement between SJVN and the Mizoram government should be signed within three months.