The Battery Energy Storage System (Bess) market in the UK was somewhat volatile in 2024. Due to the fall of income and worries about the scalability of technology and the policy environment in the UK, various large BES -investment companies have had to sell or even all their portfolios to remain their claim in the market.
Although some have had to change tack to cope with the winds of change, other companies continue to bloom. Independent Power Producer (IPP) Econergy saw a great victory in the fall of 2024, because the Swangate Bess of the company, a development of 50 MW/102MWH in Yorkshire, successfully was a route-to-market agreement and financing agreement with international banking giant Goolddman Sachs. Goldman Sachs International Bank provided financing for € 32 million (£ 27 million), the majority of which were used to pay the construction costs and to repay existing shareholders loans.
With the project now connected to the grid and the beginning of full commercial operations that are imminent, we sat down with Josh Murphy, head of storage at Econergy, to discuss the Swangate project, the recent struggles of the British Bess market and what the future is in store for the sector.
There are clearer days ahead
Although the recent past of the market has been turbulent, Murphy notes with some optimism that started to put down the last of the year Bess income, a trend that he will continue in the following year and then.
He notes that indexes such as Modo and LCP have seen Bess activa in general perform at around 100,000 per megawatt per year since October – November 2024, and since this time they are fairly consistent. He also notes that assets that have been funded by Goldman Sachs – such as the Swangate project – have been consistently achieved at £ 100,000 to £ 110,000 per MW according to Modo Energy in the past four months, a positive sign for the future potential income for the Swangate project.
The Swangate Project was connected to the Raster at the end of last year and Murphy notes that the company still performs different tests for the markets and services in which the project will be involved. Although he did not announce a timeline for when this work would be completed, he noted that he was optimistic about the progress of these efforts.
Grid connections remain a concern
It is not surprising that Murphy shares many of the frustrations that a large part of the industry of the renewable energy – not only those in the Bess sector – have the current timeline of the grid connection in the UK. He explains: “Like most European countries, grid connections are a huge bottleneck its e, and it is talked about different forums. We will do our scoping, and we will find a good location, and then the timelines are just crazy. “
Murphy attributes this grid bottleneck to a number of different factors: firstly, the abundance of so -called “zombie” projects in the queue of the connections. He notes that although Econergy, as IPP, has a high degree of skill and confidence in their projects by the time that a grid connection is submitted, this is not always the case for the developments that are in the queue for them.
“When we use a request for a grid connection, this means that we have faith in the technology. We have the money to invest in the project and build it, and the expertise to do it. It is not always the case that everyone in that queue is an experienced and serious player. So often we will find ourselves behind people who don’t really build something and they just fall in the queue. ”
Although this is something that will hopefully be resolved by Neso’s newest reforms of the network connection connection, so that developers will meet specific standards for readiness and strategic coordination with local needs, the other major problem, according to Murphy’s view, is one that is often discussed in the renewable energy sector; The green skills gap. He notes: “I think there is a huge shortage of skills and a shortage of manpower within the network operators themselves. If we are going to achieve extensive goals for 2030 and 2050, it really needs to be tackled, and these guys need the extra people to deliver the connections. ”
Technical improvements bring new possibilities
In his role as main storage for Econergy, Murphy has a considerable interest in technological developments in the energy storage sector. He remarks: “The output capacity of containers is constantly improving, just like the cyclust count, as well as safety. Those three things combined for us – if someone who invests and the project is going to own – are great signs that we can get more energy capacity from an available footprint on the ground. “
He adds that the constant fire safety improvements have also contributed to increasing investors and the trust of the public in Bess developments, making it much more likely that further Bess projects will be on the market.
Moreover, the increased technical skill of Bess developments – especially because more is capable of starting black in times of griders and synthetic slowness increasingly useful – the attractiveness of Bess -development is becoming increasingly clear.
So what is the following?
When asked what is expected to be held for the Bess market in the next five years, Murray believes that the assets that will do best are those who retain a certain degree of flexibility with how they develop and build over time.
He notes that Econergie has adopted the strategy to apply for a building permit to build up projects with a longer duration than they will initially deliver to ensure that during the 15-25-year life of the project, there is room to grow and develop as the market does.
“We want to ensure that we are the best in the classroom, so we have the flexibility to move and navigate with the market. So we would, for example, apply for a schedule for a project of six hours or an eight-hour project, so that we can have the flexibility to increase a long-or-medium-term project, because Capex can change in the market, “he says.
“As an alternative, we can see saturation in peak prices as a result of the use of many 2 -hour batteries. We want to be able to soften against this. So we want to plan for everything, and when we get the time to use it, we make our decision. ”
2025 will be an exciting year, especially for economic energy. Murphy notes that the company will probably connect more than 700 MW capacity in 2025, including a 210 MW project in Poland and various other projects in Romania, Greece and Italy.