A decision published by the Greece -Ministerie of Environment and Energy in the State Gazette Last Friday was a surprise for the domestic energy storage sector. The ministry had a public consultation at the end of February and set one New 3.5 GW energy storage program. However, the final decision is aimed at a total of 4.7 GW of new, rebellious storage projects in the field of new batteries.
Of this capacity, 3.8 GW of batteries will link to the transmission network and 900 MW of capacity will be installed on the distribution network. Independent island networks are excluded from the program. However, projects on islands that link to the electricity network of the mainland are eligible to participate in the new regulation.